150. Furnish and install
individual sets of mechanism for supporting the large draperies in front of
nine (9) mirror panels in the Grand Foyer.
Mechanism must include necessary fillet blocks between drapes, all
necessary wire guides and pipe battens, etc. to close openings in moldings.
151. Furnish and install
two (2) pipe sleeves for the cables for each of the mechanisms to slide
through.
152. These drapes
must be arranged so as to be lowered for cleaning.
153. All of the above
to be as shown on detail drawing #218, plan 5-5 and section 6-5.