GRAND FOYER DRAPERY RIGGING

150. Furnish and install individual sets of mechanism for supporting the large draperies in front of nine (9) mirror panels in the Grand Foyer.  Mechanism must include necessary fillet blocks between drapes, all necessary wire guides and pipe battens, etc. to close openings in moldings.

151. Furnish and install two (2) pipe sleeves for the cables for each of the mechanisms to slide through.

152. These drapes must be arranged so as to be lowered for cleaning.


153. All of the above to be as shown on detail drawing #218, plan 5-5 and section 6-5.